Goleta Project Connect

Building Better Connections. Overcoming Complex Conditions.

Ekwill Street and Fowler Road Extensions Project | Job 441

Improving community mobility often requires more than new roads. It demands the integration of bridges, intersections, utilities, drainage systems, and environmental improvements within an existing transportation network.

SPC is delivering a $62.7 million infrastructure improvement project for the City of Goleta, expanding roadway connectivity through Old Town Goleta while replacing the Hollister Avenue Bridge over San Jose Creek.

The project combines bridge construction, roadway extensions, roundabout improvements, creek restoration, drainage infrastructure, and environmental mitigation.

Project at a Glance

Client: City of Goleta

Location: Goleta, Santa Barbara County, California

Contract Value: $62.7 Million

Project Start: March 2024

Delivery Method: Construction Manager / General Contractor

Category: Bridges / Highways / Alternative Delivery

Status: Ongoing

Contract Value
$ 0 M
Hollister Avenue Bridge Span
0 FT
Roundabouts
0
Articulated Concrete Block Mats
0 SF
W24×250 Soldier Piles
0 LF

The Challenge

Building Around Utilities,
Traffic, and Environmental Constraints

The project involves complex construction within an established urban environment, where existing utilities, active traffic, creek conditions, and environmental restrictions influence construction sequencing.

Utility conflicts and delays have required repeated adjustments to staging plans, while construction near San Jose Creek must account for environmental requirements, including nesting and migratory birds.

Bridge replacement, roadway extensions, and work near State Route 217 ramps add further logistical demands.

The Approach

Flexibility Through Collaboration

SPC is coordinating construction of the Hollister Avenue Bridge replacement, extensions of Ekwill Street and Fowler Road, roundabout improvements, drainage systems, and associated civil infrastructure.

Self-performed operations include structural construction, excavation, grading, paving, drainage, and creek improvements.

When utility delays disrupted planned activities, SPC worked collaboratively with the City to revise construction staging and maintain progress wherever feasible.

The project also incorporates specialized bridge construction measures, including all-weather falsework supports, alongside substantial retaining and creek-protection infrastructure.

The Impact

A More Connected Goleta

The project is designed to improve mobility through Old Town Goleta by creating new roadway connections, improving intersections, and expanding pedestrian access.

Bridge replacement, drainage improvements, and creek restoration will contribute to the long-term reliability and functionality of the surrounding infrastructure.

A $24 million freeway infrastructure rehabilitation project replacing overhead signs and structures while upgrading roadway safety systems along State Route 91.

A comprehensive concrete pavement rehabilitation along Interstate 5 in Burbank, restoring structural integrity through pavement and base reconstruction within an active freeway corridor.

A comprehensive pavement rehabilitation and groundwater mitigation project addressing deteriorating roadway conditions along approximately 10 miles of SR-241 in Orange County.