Building Better Connections. Overcoming Complex Conditions.
Ekwill Street and Fowler Road Extensions Project | Job 441
Improving community mobility often requires more than new roads. It demands the integration of bridges, intersections, utilities, drainage systems, and environmental improvements within an existing transportation network.
SPC is delivering a $62.7 million infrastructure improvement project for the City of Goleta, expanding roadway connectivity through Old Town Goleta while replacing the Hollister Avenue Bridge over San Jose Creek.
The project combines bridge construction, roadway extensions, roundabout improvements, creek restoration, drainage infrastructure, and environmental mitigation.
Client: City of Goleta
Location: Goleta, Santa Barbara County, California
Contract Value: $62.7 Million
Project Start: March 2024
Delivery Method: Construction Manager / General Contractor
Category: Bridges / Highways / Alternative Delivery
Status: Ongoing
The project involves complex construction within an established urban environment, where existing utilities, active traffic, creek conditions, and environmental restrictions influence construction sequencing.
Utility conflicts and delays have required repeated adjustments to staging plans, while construction near San Jose Creek must account for environmental requirements, including nesting and migratory birds.
Bridge replacement, roadway extensions, and work near State Route 217 ramps add further logistical demands.
SPC is coordinating construction of the Hollister Avenue Bridge replacement, extensions of Ekwill Street and Fowler Road, roundabout improvements, drainage systems, and associated civil infrastructure.
Self-performed operations include structural construction, excavation, grading, paving, drainage, and creek improvements.
When utility delays disrupted planned activities, SPC worked collaboratively with the City to revise construction staging and maintain progress wherever feasible.
The project also incorporates specialized bridge construction measures, including all-weather falsework supports, alongside substantial retaining and creek-protection infrastructure.
The project is designed to improve mobility through Old Town Goleta by creating new roadway connections, improving intersections, and expanding pedestrian access.
Bridge replacement, drainage improvements, and creek restoration will contribute to the long-term reliability and functionality of the surrounding infrastructure.