Rebuilding the Airfield From the Ground Up.
Taxiway F Reconstruction, Renamed Taxiway A | Job 435
Aviation infrastructure demands precision at every level, from the stability of the subgrade to the performance of the finished pavement and the reliability of airfield lighting systems.
SPC completed a $17.9 million reconstruction of Taxiway A, formerly Taxiway F, at Oxnard Airport. The project replaced aging pavement with a stronger structural section while modernizing drainage, airfield lighting, guidance signs, and pavement markings.
Completed within an active airport environment, the project required specialized construction techniques, strict quality standards, and careful coordination around aviation operations.
Client: County of Ventura, Department of Airports
Location: Oxnard, California
Project Value: $17.9 Million
Completed: December 2024
Duration: Approximately 8 Months
Category: Airports / Heavy Civil Construction
Status: Completed
The project required extensive pavement removal and reconstruction while maintaining airport operations under strict safety and access requirements.
Subgrade conditions also differed from original design assumptions. Wet soils and varying stabilization needs required SPC to adjust treatment methods during construction.
Additional material disposal, underground utility conditions, and airfield electrical work increased the complexity of an already demanding schedule.
SPC self-performed major demolition, excavation, earthwork, aggregate-base construction, asphalt paving, drainage installation, and site restoration.
When soil conditions required changes, the team adjusted stabilization methods using cement treatment, lime treatment, and in-place drying to achieve the required subgrade performance.
The reconstruction incorporated FAA P-401 asphalt paving, upgraded drainage infrastructure, LED taxiway edge lighting, guidance signs, and extensive pavement markings.
The completed reconstruction provides renewed taxiway pavement and supporting infrastructure for aircraft traveling between the runway and airport facilities.
Improved pavement performance, drainage, lighting, signage, and markings support safer aircraft movement and long-term airfield reliability.